EXIN Agile Scrum Foundation — Question 2

A story was estimated at eight ideal hours. A working day is eight hours. Developers can get about six hours of work done on a daily basis.
What is the elapsed time required to complete the story?

Answer options

Correct answer: B

Explanation

The correct answer is B, as it takes approximately 1.33 days to complete the story. Since developers can work six hours a day, it would take them a bit more than one full day (8 hours / 6 hours per day = 1.33 days) to finish the task. Options A, C, and D do not accurately reflect the calculation based on the provided information.