EXIN Agile Scrum Foundation — Question 1
What is the usual length of the time box for the complete Sprint Planning meeting?
Answer options
- A. Four hours for a 30 day Sprint, one to two hours for a shorter Sprint.
- B. However long it takes to complete the Sprint Backlog.
- C. Never more than two hours, regardless of Sprint length.
Correct answer: A
Explanation
The correct answer is A, as the Scrum Guide specifies that Sprint Planning should last up to four hours for a 30-day Sprint, and proportionally less for shorter Sprints. Option B is incorrect because it does not define a fixed time frame, and option C is also wrong because it contradicts the guidance provided for longer Sprints.