CompTIA Project+ (PK0-005) — Question 93
During the execution of production for a bike, a PM was hired. One month later, the PM has been receiving multiple project report requests from stakeholders. Which of the following should the PM do FIRST?
Answer options
- A. Discuss the requests with the sponsor.
- B. Prepare and send the information.
- C. Assign this task to the project team.
- D. Review the communication plan.
Correct answer: D
Explanation
The correct answer is D because reviewing the communication plan will help the PM understand the established protocols for stakeholder communication and reporting. The other options, such as preparing information or discussing requests, may not be effective without first ensuring that the communication strategy aligns with stakeholder expectations.