CompTIA Project+ (PK0-005) — Question 91

A project manager is working on a project charter and has successfully documented the project objectives and the success criteria. Which of the following should the project manager define NEXT to complete the project charter?

Answer options

Correct answer: B

Explanation

The next logical step in completing the project charter after defining objectives and success criteria is to outline the Preliminary scope statement, which provides a detailed description of the project deliverables and boundaries. The other options, while important, do not directly relate to finalizing the project charter at this stage.