CompTIA Project+ (PK0-005) — Question 91
A project manager is working on a project charter and has successfully documented the project objectives and the success criteria. Which of the following should the project manager define NEXT to complete the project charter?
Answer options
- A. Proposed solution design
- B. Preliminary scope statement
- C. Responsibility assignment matrix
- D. Initial budget baseline
Correct answer: B
Explanation
The next logical step in completing the project charter after defining objectives and success criteria is to outline the Preliminary scope statement, which provides a detailed description of the project deliverables and boundaries. The other options, while important, do not directly relate to finalizing the project charter at this stage.