CompTIA Project+ (PK0-005) — Question 90
Which of the following would be the MOST beneficial to determine whether a project has met the defined objectives?
Answer options
- A. Schedule variance
- B. Cost variance
- C. Work breakdown structure
- D. Key performance indicators
Correct answer: D
Explanation
Key performance indicators (KPIs) are specifically designed to measure the success of a project against its objectives. Schedule and cost variance provide insights into project performance but do not directly assess goal achievement. The work breakdown structure is a project management tool that outlines tasks but does not measure success in meeting objectives.