CompTIA Project+ (PK0-005) — Question 9

Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?

Answer options

Correct answer: D

Explanation

Reconciling the budget is essential in the closing phase to ensure all financial aspects align with the project outcomes. While evaluating the project, releasing resources, and closing contracts are important, they do not directly address the financial accountability that reconciliation provides.