By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?

Answer options

Correct answer: A

Explanation

Allocating resources is essential to ensure that each task in the project schedule has the necessary personnel and materials assigned to it. While determining the project budget, developing a communication plan, and establishing baselines are important activities, they are not directly related to the completion of the schedule itself.