CompTIA Project+ (PK0-005) — Question 87

A project manager has been assigned to a project that involves replacing key operational equipment. The project manager is new to the industry and has learned that compliance requirements must be met. Which of the following should the project manager do FIRST?

Answer options

Correct answer: C

Explanation

The correct answer is C because understanding the compliance requirements is fundamental for the project manager to ensure that all aspects of the project align with regulations. Option A is incorrect as it assumes that documentation is sufficient without verifying compliance. Option B, while beneficial, does not provide the foundational understanding required before engaging with users. Option D incorrectly places the responsibility solely on the QA specialist instead of the project manager taking initiative to understand the requirements.