CompTIA Project+ (PK0-005) — Question 86
A portfolio manager needs to provide the senior management team with a dynamic, high-level, monthly status update on all active projects in the portfolio. Which of the following should the manager use to accomplish this task?
Answer options
- A. Dashboard
- B. Status report
- C. Gantt chart
- D. Email
Correct answer: A
Explanation
The correct answer is A, as a Dashboard provides a visual display of key metrics and project statuses, making it ideal for high-level updates. While a Status report (B) and Gantt chart (C) can convey information, they may not be as dynamic and visually engaging as a Dashboard. Email (D) is not a tool designed for this specific task and lacks the visual representation of data.