In the middle of a five-year project, a vendor asked the buyer to revisit the rate card associated with the development team. According to the vendor, the development team's experience and technical skills have increased since the project started. Which of the following documents should the buyer review FIRST?

Answer options

Correct answer: B

Explanation

The Statement of Work (SOW) is the most relevant document to review first because it outlines the specific work and deliverables expected in the project, including any rate agreements. The other documents, like the MOU, RFP, and RFI, do not detail the scope and terms of the work as closely as the SOW does.