CompTIA Project+ (PK0-005) — Question 83

Which of the following key project elements is used to organize deliverables into manageable pieces to ensure the proper steps are executed and to achieve the project's core objectives?

Answer options

Correct answer: A

Explanation

The correct answer is WBS (Work Breakdown Structure) because it is specifically designed to divide project deliverables into smaller, manageable tasks to facilitate effective execution. The other options, while important in project management, serve different purposes: RACI defines roles and responsibilities, RFP is a document for soliciting bids, and PERT is a scheduling technique.