CompTIA Project+ (PK0-005) — Question 81

A PM in a matrix organizational structure has team members who do not have adequate time to dedicate to project activities. Which of the following should the PM do to improve the team members' availability?

Answer options

Correct answer: C

Explanation

The correct answer is C because negotiating with functional managers can help secure more time or resources for the project team. Option A may lead to burnout, option B does not directly address the issue of time allocation, and option D can be costly and time-consuming without solving the immediate availability problem.