CompTIA Project+ (PK0-005) — Question 80

A PM has gathered stakeholders from across various functions in the organization. The team has never worked together before. Which of the following should the PM do to ensure standards are understood?

Answer options

Correct answer: A

Explanation

Conducting team training is essential for aligning the team on standards, especially since they are unfamiliar with each other. Presenting the scope statement, establishing meeting schedules, and developing a communication plan are important as well, but they do not directly address the need for understanding standards among team members.