CompTIA Project+ (PK0-005) — Question 376

For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

Answer options

Correct answer: D

Explanation

The RACI chart is the best choice because it clearly defines roles and responsibilities for each activity within the project. The other options, while useful for different aspects of project management, do not specifically illustrate roles related to activities as effectively as a RACI chart does.