CompTIA Project+ (PK0-005) — Question 375
A program manager is reviewing the project portfolio and prioritizing each project based on the company’s strategic plan. Which of the following should be considered in this evaluation? (Choose two.)
Answer options
- A. Company vision
- B. Global environment
- C. Brand value
- D. Mission statement
- E. Portfolio budget
- F. Local legislation
Correct answer: A, D
Explanation
The correct answers are A and D because the company vision and mission statement directly reflect the strategic direction and purpose of the organization, which are crucial for project prioritization. The other options, while relevant to the broader context, do not specifically align with the internal strategic assessment needed for prioritizing projects.