CompTIA Project+ (PK0-005) — Question 366
A project team is unclear on product deliverables. The project manager proposes gaining the feedback of subject matter experts and other interested stakeholders. Which of the following will best help the project manager better define the product deliverables?
Answer options
- A. Focus groups
- B. Tasksetting
- C. Workshop
- D. Brainstorming
Correct answer: A
Explanation
Focus groups are effective for gathering detailed feedback from stakeholders and subject matter experts, making them ideal for clarifying product deliverables. Tasksetting, workshops, and brainstorming may provide insights but are less structured for obtaining specific feedback on defined deliverables compared to focus groups.