CompTIA Project+ (PK0-005) — Question 365

The project manager notices that the contractor has not been attending the weekly project progress meetings. Which of the following actions should the project manager take?

Answer options

Correct answer: C

Explanation

The correct answer is C because enforcing the contract rules of engagement addresses the issue directly while maintaining the contractual relationship. Option A may not ensure compliance, while B is too drastic, and D does not address the attendance issue specifically.