CompTIA Project+ (PK0-005) — Question 365
The project manager notices that the contractor has not been attending the weekly project progress meetings. Which of the following actions should the project manager take?
Answer options
- A. Contact the contractor directly.
- B. Cancel the contract.
- C. Enforce contract rules of engagement.
- D. Issue a contract change notice.
Correct answer: C
Explanation
The correct answer is C because enforcing the contract rules of engagement addresses the issue directly while maintaining the contractual relationship. Option A may not ensure compliance, while B is too drastic, and D does not address the attendance issue specifically.