During the planning phase, a project manager decides to introduce a new enterprise portal toot, which has been approved by the PMO. Which of the following should be the project manager's next step?

Answer options

Correct answer: B

Explanation

The correct next step is to add training to the schedule, as ensuring that team members are adequately trained on the new enterprise portal tool is crucial for its successful implementation. Creating a transition plan, updating the project charter, or involving the CCB may be important later, but they are not the immediate priority after deciding to introduce the new tool.