A highly scored negative causes a risk trigger, but the issue has not started yet. Which of the following is the next step the project team should take?

Answer options

Correct answer: A

Explanation

The correct answer is A, as executing the contingency plan is a proactive step to mitigate the risk before it materializes. Options B and C are reactive measures that apply after a risk has occurred, and D, while important, does not address immediate action needed to manage the identified risk.