During an executive call, a project sponsor found out about issues with the project but was not able to provide details about the next steps. Which of the following needs to be revised?

Answer options

Correct answer: D

Explanation

The Communication plan needs to be revised because it should ensure that project sponsors are informed about issues and the necessary next steps. The Project dashboard, Gap analysis, and Risk register may contain valuable information, but they do not directly address the communication of next steps to stakeholders.