CompTIA Project+ (PK0-005) — Question 334
The project team is preparing to upgrade the organization's servers to comply with company standards. Which of the following should the team do first?
Answer options
- A. Develop an SOW.
- B. Prepare an issue log.
- C. Assess the compatibility.
- D. Create a rollback plan.
Correct answer: C
Explanation
The correct answer is C, as assessing compatibility is crucial to ensure that the new servers will work with existing systems and software. Without this assessment, the team risks running into major issues later in the upgrade process. Options A, B, and D are important steps but should come after determining compatibility.