CompTIA Project+ (PK0-005) — Question 330

A project sponsor wants to be aware of the project's progress by phases and tasks. Which of the following tools will satisfy this request?

Answer options

Correct answer: A

Explanation

The Gantt chart is ideal for visualizing project progress over time and allows for tracking individual tasks and phases. While a Network diagram shows task dependencies and a Project dashboard offers a summary of project metrics, neither provides the detailed timeline view that a Gantt chart does. A Work breakdown structure outlines project components but does not show progress or timelines.