CompTIA Project+ (PK0-005) — Question 329

While a team was in a work session developing the QA plan for a project, the project manager realized that the team lacks the skills required for proper quality assurance. Which of the following steps should the project manager take next?

Answer options

Correct answer: A

Explanation

The correct answer is A because reassessing the resource pool allows the project manager to identify skill gaps and potential candidates for training or reassignment. Options B and C focus on reviewing past plans or looking for additional members, which do not address the immediate skills deficiency. Option D, escalating the issue, may be necessary later but does not solve the problem at hand.