CompTIA Project+ (PK0-005) — Question 320
A project manager created an NDA document for the project team to sign due to the sensitivity of private data loaded in the production environment. Which of the following data types is the project manager most likely securing?
Answer options
- A. Restricted
- B. Personally identifiable information
- C. Confidential
- D. Internal
Correct answer: B
Explanation
The correct answer is B, as personally identifiable information (PII) pertains to sensitive data that can identify individuals, necessitating an NDA. Options A, C, and D are relevant to data sensitivity but do not specifically focus on individual privacy like PII does.