CompTIA Project+ (PK0-005) — Question 319
During project initiation, a project manager is drafting a document that includes an outline of the high-level goals, objectives, milestones, and requirements. This document will be modified and finalized as more information becomes available. Which of the following best meets the requirements?
Answer options
- A. Preliminary scope statement
- B. Procurement needs assessment
- C. Project success criteria
- D. Work breakdown structure
Correct answer: A
Explanation
The correct answer is A, the Preliminary scope statement, as it serves to outline the initial project goals and requirements, which can evolve over time. Options B and C focus on specific aspects of project management, and D pertains to detailed task breakdown rather than high-level planning.