CompTIA Project+ (PK0-005) — Question 317

Which of the following would help a project manager clearly see dependencies among tasks in a project by assisting with calculating the critical path?

Answer options

Correct answer: A

Explanation

A Network diagram is essential for illustrating the relationships and dependencies between tasks, making it easier to identify the critical path. The Project charter outlines the project's objectives but does not show task relationships, while the Project status report provides updates on progress without visualizing dependencies. A Gantt chart displays the schedule of tasks but is not as effective in showing dependencies as a Network diagram.