CompTIA Project+ (PK0-005) — Question 316
A project manager needs to prepare for the project kickoff during the initiation phase. Which of the following activities should be conducted?
Answer options
- A. Establishing accepted communication channels
- B. Developing the records management plan
- C. Reviewing existing artifacts
- D. Assessing stakeholders
Correct answer: D
Explanation
The correct answer is D, as assessing stakeholders is crucial to identify their needs and expectations, which is vital for project success. The other options, while important, do not directly relate to preparing for the kickoff in the initiation phase.