CompTIA Project+ (PK0-005) — Question 308
Which of the following activities are performed during the closing phase? (Choose three.)
Answer options
- A. Requesting project charter sign-off
- B. Recognizing project team efforts and rewarding team members
- C. Working with the financial team to obtain return of investment
- D. Revoking resource credentials from the system
- E. Updating the risk register with new findings
- F. Informing the functional manager about the release of resources
- G. Monitoring project team performance
Correct answer: B, D, F
Explanation
The correct answers are B, D, and F. During the closing phase, it's essential to recognize and reward the project team (B), revoke access for resources that are no longer needed (D), and inform relevant stakeholders such as the functional manager about resource releases (F). The other options are not typically part of the closing phase, as they relate more to planning or execution stages.