CompTIA Project+ (PK0-005) — Question 308

Which of the following activities are performed during the closing phase? (Choose three.)

Answer options

Correct answer: B, D, F

Explanation

The correct answers are B, D, and F. During the closing phase, it's essential to recognize and reward the project team (B), revoke access for resources that are no longer needed (D), and inform relevant stakeholders such as the functional manager about resource releases (F). The other options are not typically part of the closing phase, as they relate more to planning or execution stages.