Which of the following should a project manager consult when deciding how to send updates regarding deliverables?
Answer options
- A. Dashboard
- B. Status report
- C. Meeting minutes
- D. Communication plan
Correct answer: D
Explanation
The correct answer is D, the Communication plan, as it outlines the strategies and methods for delivering project updates to stakeholders. The other options, while useful, do not specifically detail how communication should be conducted.