CompTIA Project+ (PK0-005) — Question 296

During the initiation phase, a stakeholder and the project manager discuss the business reasons and benefits of the project. The stakeholder requests these items be documented for approval. Which of the following should be used to document this information?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Business case, as it is specifically designed to articulate the business reasons and benefits of a project. The Statement of work (A) outlines the scope, while the Requirements document (C) specifies detailed project requirements. The Work breakdown structure (D) is a breakdown of project tasks, not a justification for the project.