CompTIA Project+ (PK0-005) — Question 290

A project manager is meeting with business stakeholders to define the time frame for a go live to occur without impacting business operations. Which of the following is the project manager working on?

Answer options

Correct answer: B

Explanation

The project manager is establishing a Downtime window schedule to ensure that the go live occurs during a period that minimizes disruption to business operations. A Validation check, Customer notifications, and Risk analysis, while important, do not specifically address the scheduling of downtime needed for the go live event.