CompTIA Project+ (PK0-005) — Question 290
A project manager is meeting with business stakeholders to define the time frame for a go live to occur without impacting business operations. Which of the following is the project manager working on?
Answer options
- A. Validation check
- B. Downtime window schedule
- C. Customer notifications
- D. Risk analysis
Correct answer: B
Explanation
The project manager is establishing a Downtime window schedule to ensure that the go live occurs during a period that minimizes disruption to business operations. A Validation check, Customer notifications, and Risk analysis, while important, do not specifically address the scheduling of downtime needed for the go live event.