CompTIA Project+ (PK0-005) — Question 275

Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?

Answer options

Correct answer: B

Explanation

The correct answer is B because releasing project resources is essential once a project is completed to prevent team members from being tied to it. Options A, C, and D, while important, do not directly address the issue of the team member still charging time to the project.