CompTIA Project+ (PK0-005) — Question 275
Several months after a project has ended, a project team member is still charging time to the project and is unable to charge time to new projects. Which of the following did the project manager neglect to do?
Answer options
- A. Remove the team member’s access.
- B. Release the project resources.
- C. Collect the stakeholders’ feedback.
- D. Have the closeout report approved.
Correct answer: B
Explanation
The correct answer is B because releasing project resources is essential once a project is completed to prevent team members from being tied to it. Options A, C, and D, while important, do not directly address the issue of the team member still charging time to the project.