CompTIA Project+ (PK0-005) — Question 274
Which of the following contract types in project procurement has the highest risk for the buyer?
Answer options
- A. Time and material
- B. Cost-plus
- C. Fixed-price
- D. Unit price
Correct answer: B
Explanation
The Cost-plus contract type places the highest risk on the buyer because it involves paying the contractor for their actual costs plus a fee, which can lead to unpredictable expenses. In contrast, Fixed-price contracts provide more cost certainty for the buyer, while Time and material and Unit price contracts also limit risk more effectively.