CompTIA Project+ (PK0-005) — Question 237
A project sponsor requires a system that is capable of providing integrated management of all the business’s core functions. Which of the following systems is the project sponsor describing?
Answer options
- A. CMS
- B. CRM
- C. EDRMS
- D. ERP
Correct answer: D
Explanation
The correct answer is D, ERP, which stands for Enterprise Resource Planning and is designed to integrate and manage core business functions. CMS, CRM, and EDRMS serve specific purposes but do not provide the broad and integrated management capabilities that an ERP system offers.