CompTIA Project+ (PK0-005) — Question 236
A project sponsor is struggling to provide the latest project status information on a weekly executive call. Which of the following should be reviewed?
Answer options
- A. Meeting cadence
- B. Gap analysis
- C. Dashboard
- D. Adoption training
Correct answer: C
Explanation
The correct answer is C, as a dashboard provides visual representations of project status, making it easier for the sponsor to convey updates. Options A and B do not directly address the issue of sharing status information, while D focuses on training, which is unrelated to status reporting.