CompTIA Project+ (PK0-005) — Question 190

A project team has implemented a new system and needs to ensure it is usable. Which of the following should be performed first?

Answer options

Correct answer: A

Explanation

Providing end-user training is essential as it equips users with the knowledge to effectively utilize the new system, ensuring its usability from the start. Decommissioning old systems, releasing consultants, and monitoring performance are important but should follow after users are trained to use the new system effectively.