CompTIA Project+ (PK0-005) — Question 189
A project manager identifies stakeholders who will be impacted when a new product is delivered to the company. The project manager notices that more stakeholders will be positively impacted than negatively impacted. Which of the following actions should the project manager take?
Answer options
- A. List both positively and negatively impacted stakeholders.
- B. Update the communication plan with the new findings.
- C. List the negatively impacted stakeholders only.
- D. List the positively impacted stakeholders only.
Correct answer: A
Explanation
The correct answer is A because it is important to recognize both positively and negatively impacted stakeholders to ensure comprehensive communication and engagement. Ignoring negatively impacted stakeholders (as suggested in C and D) could lead to misunderstandings and resistance, while simply updating the communication plan (B) without acknowledging all stakeholders is insufficient.