CompTIA Project+ (PK0-005) — Question 115

Which of the following should occur when implementing an IT infrastructure change that takes risks into consideration?

Answer options

Correct answer: B

Explanation

Developing a rollback plan is crucial for mitigating risks associated with an infrastructure change, as it allows for a quick restoration to the previous state if issues arise. The other options, while important in the change management process, do not specifically address the risk mitigation aspect that a rollback plan provides.