CompTIA Project+ (PK0-005) — Question 114
Which of the following requires the MOST availability from the business team?
Answer options
- A. SDLC
- B. Scrum
- C. PRINCE2
- D. Waterfall
Correct answer: B
Explanation
Scrum requires continuous collaboration and regular input from the business team to adapt to changes and ensure that the product meets their needs. In contrast, frameworks like Waterfall and PRINCE2 are more structured and allow for less frequent interaction, while SDLC can vary significantly in team involvement depending on the specific approach used.