CompTIA Project+ (PK0-005) — Question 103
A project manager reviews the watch list and notices the probability of occurrence has increased for one item listed in this document; consequently, frequent monitoring is required. Which of the following tools should the project manager update NEXT?
Answer options
- A. Defect log
- B. Stakeholder register
- C. Issue log
- D. Risk register
Correct answer: D
Explanation
The correct answer is D, the Risk register, because it is specifically designed to track risks and their probabilities. Updating the Risk register is essential when the likelihood of a risk changes. The other options, such as the Defect log, Stakeholder register, and Issue log, do not pertain to risk management and therefore are not the appropriate tools to update in this scenario.