CompTIA Project+ (PK0-005) — Question 102

During a project sprint, an analyst explains multiple situations the team encountered after the previous day's sessions. The analyst then lists the tasks that need to be completed before the end of the day. Which of the following meeting types is the team utilizing?

Answer options

Correct answer: A

Explanation

The correct answer is A, Stand-up meeting, as it is a brief daily meeting where team members discuss progress, challenges, and tasks for the day. The other options do not fit the context: a Workshop meeting is for collaborative work on a specific topic, a Kick-off meeting is for project initiation, and a Presentation meeting focuses on sharing information rather than task updates.