CompTIA Project+ (PK0-004) — Question 9
A project manager procures additional resources from a local company. Which of the following-describes this event?
Answer options
- A. Reorganizing
- B. Onboarding
- C. Offshoring
- D. Outsourcing
Correct answer: D
Explanation
The correct answer is D, Outsourcing, as it refers to obtaining services or resources from an external source rather than using internal resources. Reorganizing involves changing the structure of a team, onboarding pertains to integrating new employees, and offshoring means relocating business processes to another country, which does not apply here.