CompTIA Project+ (PK0-004) — Question 8
A project team has determined it will need to source data from a system that was not part of the project scope.
The role of the project manager is to analyze which of the following impacts?
Answer options
- A. Technical design, schedule, and budget
- B. Business process impacts and resourcing
- C. New software and hardware requirements
- D. Schedule, budget, and quality
Correct answer: C
Explanation
The correct answer is C, as sourcing data from an external system typically requires new software and hardware to facilitate integration. The other options, while relevant to project management, do not directly address the implications of introducing new data sources into the project.