CompTIA Project+ (PK0-004) — Question 85

A project manager is planning to hold a meeting to discuss what went well, what did not go well, and what should be done differently. Which of the following meetings should the project manager hold?

Answer options

Correct answer: D

Explanation

The correct answer is D, as a Status meeting focuses on reviewing project progress and discussing what worked and what didn't. A Kickoff meeting (A) is for starting the project, an Impromptu meeting (B) is unplanned, and a Closure meeting (C) typically occurs at the end of a project rather than during its progress.