CompTIA Project+ (PK0-004) — Question 84
Which of the following organization types requires the project manager to report performance issues to another department?
Answer options
- A. Functional
- B. Strong matrix
- C. Projectized
- D. Weak matrix
Correct answer: D
Explanation
In a Weak matrix organization, the project manager has limited authority and often reports to a functional manager, which necessitates the reporting of performance issues to another department. In contrast, the Functional organization has clear departmental divisions, while Strong matrix and Projectized organizations grant more authority and autonomy to project managers, reducing the need for such inter-departmental reporting.