CompTIA Project+ (PK0-004) — Question 63

A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed?
(Choose two.)

Answer options

Correct answer: B, E

Explanation

To accommodate significant changes in project scope, the Project schedule (B) must be updated to reflect new timelines, and the WBS (E) needs to be adjusted to include the new deliverables and tasks. The other options, while relevant to project management, do not directly relate to the necessary adjustments in scope.