CompTIA Project+ (PK0-004) — Question 563
A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?
Answer options
- A. Submit a change request.
- B. Evaluate the impact of the change.
- C. Get approval from the CCB.
- D. Communicate the change to stakeholders.
Correct answer: B
Explanation
Evaluating the impact of the change is essential to understand how it will affect the project before proceeding. Submitting a change request and getting approval are steps that follow the impact assessment, while communicating to stakeholders is also premature without first understanding the implications of the change.