CompTIA Project+ (PK0-004) — Question 563

A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?

Answer options

Correct answer: B

Explanation

Evaluating the impact of the change is essential to understand how it will affect the project before proceeding. Submitting a change request and getting approval are steps that follow the impact assessment, while communicating to stakeholders is also premature without first understanding the implications of the change.