While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:
Answer options
- A. quality plan.
- B. project management plan.
- C. risk register.
- D. process diagram.
Correct answer: A
Explanation
The quality plan outlines the metrics and standards for quality, including those for evaluating risks. While the project management plan provides a broader overview of the project, it does not focus specifically on qualitative scales. The risk register contains identified risks but does not provide guidance on the scales themselves. The process diagram visualizes workflows but does not address qualitative assessments.