CompTIA Project+ (PK0-004) — Question 533
An influential stakeholder has left the organization. Which of the following documents MOST likely needs to be updated?
Answer options
- A. Incident response plan
- B. Issue log
- C. Communication plan
- D. Project plan
Correct answer: C
Explanation
The correct answer is C, as the communication plan outlines how information is shared with stakeholders, and a change in a key stakeholder necessitates updates to ensure proper communication channels are maintained. The other options, while important, do not directly relate to stakeholder communication and may not require immediate updates due to a personnel change.