CompTIA Project+ (PK0-004) — Question 532

As part of a project, employee production cannot proceed unless certain thresholds of the product are achieved. Which of the following is this called?

Answer options

Correct answer: D

Explanation

The correct answer is 'Quality gate' because it refers to checkpoints that must be met regarding the quality of the product before progressing. The other options, such as 'Critical path', 'Milestone', 'Phase gate', and 'Toll gate', refer to different project management concepts that do not specifically denote quality thresholds for production.